AUGUST 2018

CONSTRUCTION UPDATE - AUGUST, 2018

The Centrepiece Residence development is underway, with construction progressing well on site.

Read more

The builder has completed the guide wall system and is currently installing the basement retention system, with 92 of the 525 contiguous piles installed to date.

With some luck with the weather, we should have the basement retention system complete towards the end of September. This will allow the large bulk excavation to commence.

We have also seen solid progress with the major authority services diversion works and connection works. The sewer line has been successfully diverted around the site, with these works been completed on the 3rd of August.

The stormwater connection works have also commenced, with completion of this expected in September. The build time for this project is approximately 18 months.

Close

JUNE 2018

Construction Update - June, 2018

The development team is happy to report that works are progressing well on site.

Read more

Demolition is complete and the site is being prepared for basement piling which is due to commence in the second week of July 18.

There will be over 525 contiguous piles to be installed at an average of 12 meters in length over the next 8 weeks. These piles will retain the double basement during excavation works.

The major sewer diversion works are also tracking well and are scheduled for completion in early July 18.

The development team is excited for the months ahead as the retention and excavation works mobilise on site. You will see some major activity over the coming months with large piling (drilling) rigs on site as these works commence.

Please refer to the next pages for some site progress photos.

Also don?t forget to visit our Launch Corporation Facebook page to get all the latest project updates and videos by clicking the following icon.

Should you have any general queries in regards to our project please do not hesitate to contact Ms. Joanne Arbid. Her details are below:

Email: joannea@launchcorp.com.au

Contact: 1300 733 175

Close

DECEMBER 2017

Construction Update - December, 2017

Thank you again for your patience as we finalise the very last stages of our construction program with our appointed builders for Centrepiece Residences.

Read more

This project has been a little trickier to mobilise than others and we are well aware that the delays have been extremely frustrating for everyone. However, we can assure you that we are doing everything within our capabilities to speed up the process during the construction stage to make up for lost time.

We are pleased to report that the display suite has been stripped and ready for demolition. The delay for demolition commencing was attributed to the abolishment of services including Gas, Electrical and Water Meters with authorities that took over 4 months to process. These have now been all terminated and removed from the site.

We have also completed the removal of all asbestos in the buildings pursuant to the environmental auditors? report in preparation for demolition.

Demolition has finally commenced on site with the program showing all residential buildings demolished this side of the New Year. The Commercial building on the corner of Centre Road, and East Boundary Road is scheduled for demolition in the 2nd week of January 2018. Once construction commences we will arrange for quarterly updates as we get underway with building Centrepiece Residences.

As mentioned in earlier communication, Ms. Joanne Arbid is your first point of contact to assist you with any of your queries. Her details are below:

Email: joannea@launchcorp.com.au

Contact: 1300 733 175

Close